Project List | |
Accept Sales Agreement | 11/22/2005 |
Contact Customer for Design Center Appt. (est.) | 12/09/2005 |
Site Meeting | 11/23/2005 |
Deadline for Structural Changes | 12/06/2005 |
Design Center Appt. (est.) | 12/16/2005 |
Check Print Ready for Approval | 12/29/2005 |
Berks Homes Receipt of Buyer-Approved Check Print | 01/13/2006 |
Stake Lot | 01/20/2006 |
Building Permits Received | 02/02/2006 |
Berks Homes to Call for Pre-construction Meeting | 02/14/2006 |
Prints Approved/Released to Field | 02/10/2006 |
Excavate Foundation | 02/14/2006 |
Pour Footers | 02/16/2006 |
Set Foundation Walls | 02/21/2006 |
Remove Foundation Forms | 02/23/2006 |
Foundation Backfill | 03/02/2006 |
First Floor Framing | 03/09/2006 |
Roof Trusses | 03/14/2006 |
Plumbing Rough-in | 03/17/2006 |
HVAC Rough-in | 03/17/2006 |
Berks Homes to Call for Pre-drywall Meeting | 03/17/2006 |
Electrical Rough-in | 03/22/2006 |
Pour Basement/Garage Concrete Floors | 03/24/2006 |
Vinyl Siding | 03/28/2006 |
Insulation | 03/29/2006 |
Drywall | 04/06/2006 |
Trim | 04/24/2006 |
Interior Paint | 04/28/2006 |
Vinyl Floors | 05/01/2006 |
Hardwood Floors (if applicable) | 05/02/2006 |
Cabinets | 05/03/2006 |
Berks Homes to Call for Color Confirmation | 05/04/2006 |
Ceramic Tile Install (if applicable) | 05/09/2006 |
Plumbing Finish | 05/11/2006 |
Electrical Finish | 05/12/2006 |
Berks Homes to Call for Orientation | 06/06/2006 |
Carpet | 05/17/2006 |
Final Cleaning | 05/25/2006 |
Orientation | 06/06/2006 |
Closing | 06/07/2006 |
Settlement | 06/22/2006 |